February 2004

 

2/3-2/6:  Finished making the Lake Placid trail handicapped accessible with the AmeriCorps group.

2/9-2/12:  Worked on rock steps/ viewing platforms above spillway.  Built one long retaining wall for the lower viewing platform, and built three big stone steps up to larger viewing platform.  Started on the upper viewing platform, moving huge rocks into place.

2/16-2/20:  Finished up large retaining wall for upper viewing platform.  Finished moving huge rocks into place (1600-2000 # rocks) and filled platform in with fill dirt.  Cut about 300' of trail on the connector.  On Saturday, we had a very large volunteer day.  We had 42 volunteers show up from Christ Church and worked on the connector trail.  We got a lot done and had a really nice day.

2/24-2/26:  Cut another section of the connector trail.